CT Meter Shows Half Current on Generator Switchover

By editor 7 min read
Two parallel cables with a current transformer clamped around only one, feeding a meter that reads half, beside a generator and transfer switch

If a CT-fed meter shows about half the real current after switching to the generator, the CT is almost certainly seeing only part of the current path. Check whether the CT encloses all of the parallel conductor sets on that phase, whether one of two paralleled CTs is open, whether the meter’s CT setting matches the CT, and whether the generator current flows through the same conductors the CT surrounds. A clamp meter around every conductor of the phase tells you which.

SymptomLikely causeCheck
Reads exactly half, on both sourcesCT setting half the fitted CT, or CT on one of two parallel setsMeter CT amps setting; how many conductors pass through the CT
Half only on generatorGenerator feeds through a set the CT does not enclose, or one paralleled CT is in the unused pathTrace the generator conductors through the transfer switch
Zero on generatorCT on the utility side of the transfer switchMove the CT to the load side
Negative or near zeroCT reversed, or reversed paralleled CTs cancellingCT arrow and lead polarity
Amps right, kW wrongCT on the wrong phase for its voltage inputMatch CT phase to voltage phase
Based on Continental Control Systems, Schneider Electric and RDL CT installation guidance.
Safety: Work inside live switchgear needs a qualified person, the right PPE and an approved procedure. Never open a current-output CT secondary while the primary carries current.

Cause 1: The CT Sees Only One Parallel Set

CT around one or both parallel conductor setsTwo parallel conductor sets each carry 400 amps. A CT around only one set reports 400 amps of the real 800 amps. A CT around both sets reports the full 800 amps.Why a CT on one of two parallel sets reads halfCT around one set onlySourceLoad400 A400 AMeter shows 400 A of 800 ACT around both setsSourceLoad400 A400 AMeter shows 800 AIndustrialBasicsindustrialbasics.com
Figure 1: Based on Continental Control Systems guidance on measuring parallel conductors.

Large services and feeders use parallel conductors. Continental Control Systems (CTL) explains that two or more sets of phase conductors are run in separate conduits and joined at both ends, and that this is common for 400 A and larger circuits. Main switchboards, covered in our guide to what switchgear is, are where these sets usually land. Because one CT big enough to fit all of them is awkward, installers sometimes put a CT around only one conductor per phase and multiply the result.

CTL says this approach “is generally not recommended” because the current may not be equal in all conductors, caused by variations in length and in the connections at each end. If the current is not equal, readings can be consistently high or low. On generator power, the conductors and terminations change, so the sharing can change too. If the meter was never scaled for the number of sets, it simply reads 1 ÷ n of the real current.

Cause 2: One of Two Paralleled CTs Is Open

The other way to measure parallel sets is one CT on each set, with the leads paralleled at the meter. CTL says the effective CT amps is the sum of the individual ratings, so two 400 A CTs are set as 800 A, and all paralleled CTs must be exactly the same part number. If one of two CTs is disconnected, damaged or left off the conductor, the meter loses half its signal and reads half.

CTL also warns that more CTs make wiring errors harder to spot, because an error is “only a fraction of the total power”. It recommends adding one set of CTs at a time and checking the reading each time.

Cause 3: The CT Is on the Wrong Side of the Transfer Switch

CT location and the transfer switchA CT on the utility conductors upstream of the transfer switch only measures utility current. A CT on the load side of the transfer switch measures current from either source.CT position relative to the transfer switchUtilityGeneratorTransferswitchLoadsCT here: utility onlyCT here: both sourcesA load-side CT reads the same on utility or generator. A line-side CT reads nothing on generator.IndustrialBasicsindustrialbasics.com
Figure 2: Simplified single-line view of one phase.

A CT only measures current flowing through its window. If it is installed on the utility conductors ahead of the transfer switch, it cannot see generator current at all. If the generator connects at a point where only some conductors pass through the CT, the meter reads part of the load. To meter both sources, the CTs must be on the load side of the transfer switch, around every conductor of each phase.

Cause 4: Settings, Polarity and Phase

  • CT ratio setting: RDL’s installation notes say CTs must be the correct ratio for the meter, for example 200:5 A. A meter set for 400 A with an 800 A CT reads half on every source.
  • Polarity: CTL says a reversed CT, mechanically or electrically, reads zero or negative energy for that phase, depending on the meter. Schneider says the polarity mark (H1 or equivalent) faces the source.
  • Phase matching: CTL says each CT must be on the phase that matches the meter’s voltage input. RDL makes the same point for its meters. Our 3 phase calculations guide shows how amps, volts and kW relate.
  • CT window: CTL says the opening should not be more than 50% larger than the conductor, and the conductor should be centred for best accuracy.

Reading Check Tool

CT Meter Reading Check
IndustrialBasics troubleshooting aid. Measure with a clamp meter rated for the circuit, by a qualified person, with the panel safe to open.

Enter what the meter shows and what a clamp meter reads around all conductors of the same phase. The default values show the classic case: two parallel sets, CT on one, meter reading 410 A of a real 820 A.

Step-by-Step Troubleshooting

  1. Record the meter reading on utility and on generator at similar loads.
  2. Measure the real current with a clamp meter around all conductors of each phase, or each set in turn and add them.
  3. Count the conductor sets per phase and how many pass through each CT.
  4. Read the meter’s CT setting and compare with the CT label.
  5. Trace the generator path through the transfer switch and confirm it passes through the CTs.
  6. Check polarity and phase of every CT.
  7. Fix and re-test on both sources. If you add CTs, CTL suggests adding one set at a time.

For CT ratings and accuracy classes, see our CT ratio 1200/5 guide. For backup power arrangements, see types of UPS, and for protection relays fed from CTs, see types of protection relays.

Frequently Asked Questions

Why does my CT meter show half the current?

The most common causes are a CT around only one of two parallel conductor sets, one of two paralleled CTs open or disconnected, or a meter CT setting that is half the real CT rating. Check with a clamp meter on all conductors of the phase.

Why does the reading change when we switch to the generator?

Something about the current path changes. The generator may feed through a different conductor set, the current may share unequally between parallel conductors, or the CT may be on the utility side of the transfer switch.

Can I measure parallel conductors with one CT on one conductor?

Continental Control Systems says this is generally not recommended, because current may not be equal in all conductors. Readings can be consistently high or low.

How do I set the meter for paralleled CTs?

CTL says the effective CT amps equals one CT’s rating times the number of CTs on that phase. Three 400 A CTs in parallel are set as 1,200 A, and all must be the same part number.

Which way does a CT face?

The marked side, such as H1, P1 or “source this side”, faces the source. Schneider and CTL both say to face the polarity mark toward the line or source side.

What happens if a CT is on the wrong phase?

CTL says each CT must be on the phase that matches the meter’s voltage input. A mismatch gives wrong power and power factor even if amps look right.

Is it safe to disconnect a CT secondary?

Not for current-output CTs while primary current flows. Schneider warns that leaving the secondary open can create hazardous voltages. Short the secondary first. CTL notes its 0.333 V output CTs are internally burdened.

How do I prove the meter is right?

Compare it with a clamp meter or portable power analyzer around all conductors of each phase, on both utility and generator.

Sources and Further Reading