How to Select a PLC: Define I/O, Power and Interfaces

By editor Updated 8 min read
PLC rack with power, CPU and I/O modules connected to input sensors above and a motor, valve and lamp below

To select a PLC, first define your I/O: list every sensor and actuator, classify each signal, and add spare capacity. Then match the input and output types, check the power budget and choose the communication interfaces you need. Defining I/O first matters because the point count and signal types decide which controller family, modules and power supply will fit.

StepWhat to defineResult
1. I/ODigital, analog and specialty pointsChannel count
2. SignalsVoltage, sinking or sourcing, signal rangeModule types
3. MarginSpare points for future changesFinal module count
4. PowerSupply and backplane currentPower supply size
5. InterfacesHMI, drives, remote I/O, networksPorts and protocols
The core PLC selection sequence.
Safety first: A general-purpose PLC is not safety rated. Do not rely on one to perform an emergency stop or other safety function. Use a device rated for the hazard level.
25%
Suggested I/O margin
4–20 mA
Common analog signal
1 A
Per side on a 2 A supply
5
Selection steps
Five steps to select a PLCA sequence of five steps: define I/O, match signals, add margin, budget power and pick interfaces.Select a PLC in this order1Define I/OCount and classify2Match signalsVoltage, sink, source3Add marginPlan for growth4Budget powerSupply and backplane5Pick interfacesNetworks and HMIIndustrialBasicsindustrialbasics.com
Figure 1: Defining I/O first gives every later decision real numbers to work with.

Define I/O: Count Every Input and Output

I/O means input and output. Inputs bring information into the PLC, and outputs let it act on the machine. If you need to define IO for a project, start with the electrical drawings or walk the machine and record each device.

Field devices mapped to digital and analog I/OInput devices such as push buttons, limit switches and level sensors map to digital inputs, temperature maps to analog input, and output devices such as starters, valves and lamps map to digital outputs, with a drive speed signal as an analog output.Turn the field device list into I/OPush buttonsLimit switchesLevel sensorTemperatureDigital input / outputOn or off signalsAnalog input / outputContinuous valuesMotor starterSolenoid valvePanel lampDrive speed signalIndustrialBasicsindustrialbasics.com
Figure 2: Classify every device before counting channels.
TypeSignalTypical devices
Digital inputOn or offPush buttons, limit switches, proximity sensors
Digital outputOn or offMotor starters, solenoids, panel lamps
Analog inputContinuous valueTemperature, distance, level or pressure measurement
Analog outputContinuous valueSpeed reference or signal to another controller
SpecialtyFunction-specificHigh-speed counting or positioning
Classify every point before choosing hardware.

For more on the devices themselves, see our guide to types of industrial sensors. If the term PLC is new to you, start with what a PLC is and how it works.

Add spare capacity

Projects change, so do not size the PLC to the exact count. DigiKey’s applications guidance suggests adding 25% to your initial I/O estimate. Use your own specification if it sets a different margin.

Required points = Counted points × 1.25

Match the Input and Output Types

A correct point count is not enough. Each module must also match the voltage and electrical behavior of the device connected to it.

Sinking and sourcing

A PNP transistor output sources current, while an NPN output sinks it. A sourcing device needs a sinking input, and a sinking device needs a sourcing input. Some modules accept both. Rockwell’s 1769-IQ16, for example, is a 24 V DC sinking or sourcing input module. Confirm the connection from the wiring diagram for your exact module.

Output types

OutputStrengthLimitGood for
Transistor (PNP or NPN)Faster switchingLower current, specific voltageSmall DC loads and fast signals
RelayIsolated contacts, higher current, mixed voltagesSlower than transistorContactors and mixed loads
PWM or pulseVariable or fixed pulse outputNeeds a compatible devicePulse-driven equipment
AnalogContinuous voltage or currentUsually a signal, not powerDrive speed reference
Common PLC output types.

Larger loads are normally switched through a contactor. Our comparison of contactors and relays explains which fits a given load. For drive speed signals, see potentiometer speed control.

Analog signal ranges

DigiKey lists typical analog output ranges as 1 to 5 V, 0 to 10 V, 0 to 20 mA and 4 to 20 mA. Match the range at both ends of the signal, and check the module’s accuracy against what the process needs.

Check the Power Budget

Some PLCs include a power supply and others need a separate module. Check the allowed supply voltage range, because voltage outside that range can damage the device. On a modular system, also add up the backplane current drawn by the modules.

Rockwell’s Compact I/O guide shows how this works. Its 1769-PA2 supply provides 2 A at 5 V DC and 0.8 A at 24 V DC, and the 5 V capacity is split as 1 A to each side of the supply.

SupplyInput5 V DC bus24 V DC bus
1769-PA2120 or 240 V AC2 A0.8 A
1769-PB224 V DC2 A0.8 A
1769-PA4120 or 240 V AC4 A2 A
1769-PB424 V DC4 A2 A
Output bus capacity from 0 to 55°C, Rockwell 1769-SG002C (March 2004). Check the current publication for new designs.

Worked Example: Sizing the I/O and Power

A small machine has 34 digital inputs and 20 digital outputs, all at 24 V DC. We will use 16-point Rockwell 1769 modules as the example.

ItemInputsOutputs
Counted points3420
With 25% margin42.5, round up to 4325
16-point modules3 × 1769-IQ162 × 1769-OB16
Installed points4832
5 V current per module115 mA200 mA
5 V current total345 mA400 mA
Example I/O and backplane calculation.
3 × 115 mA + 2 × 200 mA = 745 mA at 5 V DC
Backplane current exampleA 1769-PA2 supply with three IQ16 modules at 115 mA and two OB16 modules at 200 mA on one side, totaling 745 mA against a 1000 mA per side limit.Check the current on each side of the supply1769-PA22 A at 5 VIQ16115 mAIQ16115 mAIQ16115 mAOB16200 mAOB16200 mA745 mA at 5 V on one side, against a 1,000 mA limit per sideIndustrialBasicsindustrialbasics.com
Figure 3: Module load only. Add the controller and any other modules on that side.

With all five modules on one side of a 1769-PA2, the 745 mA module load is within the 1 A limit for that side. The check is not finished yet. You must also include the controller and any other modules, and check the 24 V bus and the power supply distance rating. If demand is at or near the limit, add another I/O bank or a larger supply.

Choose the Communication Interfaces

List everything the PLC must talk to: the programming device, HMI, drives, remote I/O and plant systems. Check whether each port is built in or requires a separate module.

InterfaceMax devicesMax cable length
RS-232C115 m (50 ft)
RS-422101,219 m (4,000 ft)
RS-485321,219 m (4,000 ft)
DeviceNet63500 m (1,640 ft)
EtherNet/IPSee vendor data100 m (328 ft)
EtherCATSee vendor data100 m (328 ft)
Typical limits listed by DigiKey. Actual limits depend on speed, cable and hardware.

If you are wiring a serial link, our DB9 pinout guide covers RS-232 connections. To decide whether a PLC is the right platform at all, see PLC vs DCS vs SCADA. Programming language support is covered in our guide to IEC 61131-3.

Final PLC Selection Checklist

  • Every device is listed and classified.
  • Spare capacity has been added.
  • Input and output voltage types match the field devices.
  • Sinking and sourcing connections have been checked.
  • Analog ranges match at both ends.
  • Supply voltage and backplane current are within limits.
  • All communication ports and protocols are available.
  • Programming software and controller family are confirmed.
  • Safety functions use suitably rated devices.
Safety note: Machine safety functions need their own design and rated hardware. See our guides to NFPA 79 and light curtain safety relays. This guide is educational and does not replace manufacturer data or applicable standards.

Before standardizing on any controller family, check its lifecycle status so you do not design in a product that is already Active Mature.

If you are choosing within the Siemens range, see our S7-1200 vs S7-1500 comparison.

Frequently Asked Questions

What does it mean to define I/O for a PLC?

It means listing every field device the PLC must read or control, then classifying each as a digital or analog input or output with its voltage and signal type.

How do I count I/O for a PLC?

Go through the machine or process device by device. Count inputs such as switches and sensors, and outputs such as motor starters, solenoids and lamps, then add a margin for future changes.

How much spare I/O should I allow?

DigiKey’s applications guidance suggests adding 25% to the initial estimate. Your project specification or company standard may set a different figure.

What is the difference between digital and analog I/O?

Digital I/O handles discrete on or off states. Analog I/O handles continuous values, such as 0 to 10 V or 4 to 20 mA signals.

Should I choose relay or transistor outputs?

Transistor outputs are faster but have lower current capability and a specific voltage. Relay outputs are isolated and can switch different voltages and higher currents, but they are slower.

What is a PLC power budget?

It is a check that the power supply can deliver the current drawn by the controller and modules. On modular systems, this includes the backplane current at each voltage.

Which communication interface does a PLC need?

Choose it from what must connect to the PLC, such as HMIs, drives, remote I/O and plant networks. Check whether the port is built in or needs a separate module.

Can a standard PLC handle an emergency stop?

No. A general-purpose PLC is not safety rated. Emergency stop and other safety functions should use a device rated for the hazard level.