Lockout/Tagout (LOTO) Procedure: Step-by-Step Guide

By editor Updated 21 min read
Lockout tagout procedure guide with a padlock, by IndustrialBasics

The lockout tagout procedure, often called the LOTO procedure, is the set of steps that makes a machine safe to work on. You shut the machine down, cut off every energy source, lock or tag each isolation point, release any stored energy, and prove the machine is dead before anyone starts work.

The short answer: the 6 lockout/tagout steps

  1. Prepare: know every energy source, its size and its hazards.
  2. Shut down: stop the machine using its normal stop controls.
  3. Isolate: operate every energy-isolating device, such as breakers, disconnects and valves.
  4. Apply locks or tags: fix them to each isolating device.
  5. Control stored energy: release, drain, block or restrain it.
  6. Verify: prove the machine is isolated and de-energised before work starts.

Tell affected employees before you apply the locks and again after you remove them. These steps follow OSHA 29 CFR 1910.147(d).

Last verified: 8 November 2026

This guide explains each step in plain English. It also covers what a written procedure must contain, when a tag can replace a lock, the exceptions, electrical isolation, and how the rules differ in the US, UK and India. You will find a checklist and a template layout near the end.

3 million
US workers who service equipment and face the greatest risk (OSHA)
120 / 50,000
Deaths and injuries OSHA estimates the standard prevents each year
24 days
Average time lost by workers injured by hazardous energy (OSHA)

What Is Lockout/Tagout (LOTO)?

Lockout/tagout is a safety method that stops equipment starting up, or releasing stored energy, while someone is servicing it. OSHA calls the rule the control of hazardous energy.

Hazardous energy is any energy that could hurt someone if it were released unexpectedly. Switching a machine off at the control panel is not enough, because the supply is still connected and energy may still be stored inside.

Energy typeExampleHow it is controlled
ElectricalMains supply, capacitors, batteriesOpen and lock the disconnect or breaker, discharge capacitors, test for voltage
MechanicalFlywheels, rotating shafts, springsWait for movement to stop, then block or restrain parts
HydraulicPressurised oil in rams and linesClose and lock valves, release pressure, check gauges
PneumaticCompressed air in lines and receiversClose and lock the air supply, then vent the system
GravitationalA raised press ram or lifted loadLower it or fit mechanical blocks or pins
ThermalHot surfaces, steam linesLet them cool and isolate the heat source
ChemicalPressurised or reactive process fluidsIsolate with valves or blanks, then drain and purge as the site procedure states
Stored (residual) energy is whatever is left after the machine stops. It is the energy people forget most often.

When Is a Lockout/Tagout Procedure Required?

You need LOTO when someone services or maintains equipment and could be hurt by an unexpected start-up or release of energy. Servicing and maintenance includes installing, setting up, adjusting, inspecting, modifying, repairing, lubricating, cleaning and clearing jams.

Normal production work is not usually covered. Servicing during production is covered if a worker must remove or bypass a guard or safety device, or must enter the danger zone while the machine could operate. The general industry standard also excludes construction, agriculture and maritime work, which have their own rules.

Who is responsible for LOTO?

RoleResponsibility
EmployerWrites the energy control programme and machine-specific procedures, supplies devices, trains staff and inspects at least once a year
Authorised employeeLocks or tags out the equipment to carry out servicing, following the procedure
Affected employeeOperates the machine or works nearby, and must understand what the locks and tags mean
Other employeesAnyone else in the area, who must never try to restart locked or tagged equipment
LOTO applies wherever machines can start or release energy during maintenance, including manufacturing, food processing, chemicals, pharmaceuticals, warehousing, utilities and electrical maintenance.

Lockout Tagout Procedure: The 6 Steps Explained

The six steps below follow the order in OSHA 29 CFR 1910.147(d). Your own written procedure for each machine must be more specific than this guide.

The six lockout/tagout steps1PrepareKnow the energy sources2Shut downNormal stop controls3IsolateOperate every isolator4Lock / tagOn each isolating device5Stored energyRelease, drain, block6VerifyProve zero energyNotify affected employees before step 4 and again after the devices are removed.
Figure 1: The six lockout/tagout steps in order (simplified from OSHA 29 CFR 1910.147(d)).

Step 1: Prepare for shutdown

  • Identify the machine and the job to be done.
  • List every hazardous energy source, how big it is and what it can do.
  • Find every energy-isolating device and read the machine’s written procedure.
  • Tell affected employees that servicing is about to start.

An energy-isolating device physically blocks energy. Manually operated breakers, disconnect switches and line valves count. Push buttons, selector switches and other control devices, such as a contactor or relay, do not.

Step 2: Shut down the equipment

  • Stop the machine with its normal stop controls, in an orderly way that does not create new hazards.
  • Check that all movement has stopped.

Stopping the machine is not isolation. The supply is still live.

Step 3: Isolate all energy sources

Operate every isolating device so the machine is cut off from each source. That means opening circuit breakers and disconnects, closing valves and disconnecting any other supply. Look for sources that are easy to miss, such as a second power feed, separate control power or a supply that can back-feed from another system.

A breaker that has tripped, or a blown fuse, is not isolation. Protective devices clear faults and can be reset or replaced, as the comparison of a fuse and a circuit breaker shows.

Step 4: Apply lockout/tagout devices

  • Each authorised employee fits their own lock, and a tag where used, to every isolating device.
  • The lock must hold the device in the safe or off position.
  • The lock or tag must identify who applied it, and only that person holds the key.
  • Fit tags at the same point as the lock, or as close as is safe.

Step 5: Release or control stored energy

  • Capacitors: discharge them. A variable frequency drive (VFD) can hold a charge in its DC-link capacitors for several minutes, so check the manual.
  • Springs: release or restrain them.
  • Hydraulic and pneumatic lines: bleed or vent the pressure.
  • Raised parts: lower them or block them mechanically.
  • Hot parts: allow them to cool.

If energy can build up again, for example pressure from a process line, keep checking until the work is finished.

Step 6: Verify the zero-energy state

Verification catches the energy source you missed. Do it every time, even if you fitted the locks yourself.

  • Check that nobody is exposed to the machine.
  • Do a try-out test: press the normal start controls and confirm nothing moves, then return the controls to off or neutral.
  • Check that pressure gauges and other indicators read zero.
  • For electrical equipment, a qualified person must also test for voltage (see electrical LOTO below). A try-out test does not replace a voltage test.
  • Recheck if stored energy could re-accumulate.

What Is the Difference Between a 6-Step and 8-Step LOTO Procedure?

Neither is a different rule. OSHA’s standard lists six elements for applying energy control. Many guides show seven, eight or ten steps because they split the same job into smaller actions, or add employee notification and restoration. OSHA’s own sample procedure in Appendix A is non-mandatory and uses eight application steps, followed by steps for restoring equipment.

Six-step sequence (OSHA)Expanded approach (eight steps)
PreparationPreparation and notification
ShutdownEquipment shutdown
IsolationEnergy isolation
Lockout/tagout applicationDevice application and confirmation
Stored energy controlRelease and restraint
VerificationZero-energy verification
Not a separate stepWork completion and restoration
Not a separate stepEmployee notification and documentation
Use the step count in your employer’s written procedure. What matters is that no element is missed.

What Should a Written Lockout/Tagout Procedure Include?

The energy control programme is the employer’s overall system: procedures, training and annual inspections. A procedure is the machine-specific instruction sheet. OSHA 1910.147(c)(4) requires employers to develop, document and use written procedures.

What a procedure must contain

A procedure must set out its scope, purpose, authorisation, rules and techniques, and how compliance is enforced. It must also give specific steps for:

  • Shutting down, isolating, blocking and securing the machine.
  • Placing, removing and transferring locks and tags, and who is responsible for them.
  • Testing to confirm the isolation works.
  • The procedure’s intended use.

See the template layout below for the fields to record.

When can you skip the written procedure?

Only if all of these are true for that machine:

  • It has no stored or residual energy, and none can re-accumulate.
  • It has one energy source that is easy to identify and isolate.
  • Isolating that source completely de-energises the machine.
  • One lockout device is enough to lock it out.
  • That device stays under the exclusive control of the authorised employee.
  • Servicing creates no hazard for other employees.
  • There has been no accident involving unexpected start-up or re-energisation of the machine.

This removes the paperwork only. You must still lock out.

Can one procedure cover several machines?

Only if the machines have the same energy sources and the same isolation steps. Machines that look alike often differ, so a qualified person should check each one before sharing a procedure.

Lockout vs Tagout: What Is the Difference?

FeatureLockoutTagout
What it isA lock holds the energy-isolating device in the safe positionA warning tag states the device must not be operated
ProtectionPhysical barrierWarning only
IdentificationLock identifies its ownerTag identifies the employee who applied it
RemovalBy the person who applied it, unless the employer’s exception procedure appliesSame rule
When it is usedWhenever the device can be lockedOnly if the device cannot be locked, or the employer proves equal protection

Is lockout better than tagout?

Yes. A tag is a warning, not a barrier. It can be ignored or fall off. If an employer uses tagout on a device that can be locked, it must show full protection equal to lockout, with extra measures such as removing an isolating circuit element, blocking a controlling switch, opening an extra disconnecting device or removing a valve handle.

What makes a lockout device suitable?

  • Durable: it withstands the conditions where it is used.
  • Standardised: the same colour, shape or size within the site.
  • Substantial: it cannot be removed without excessive force or tools such as bolt cutters.
  • Identifiable: it shows who applied it.

Tags must carry a clear warning such as “Do Not Start” or “Do Not Open”. They must be non-reusable, attachable by hand and self-locking, with a release strength of at least 50 lb (about 23 kg). A good tag also shows the person’s name, the machine and, at many sites, the date. Common devices include padlocks, hasps, breaker lockouts, valve lockouts, plug lockouts, cable lockouts and group lock boxes.

Breaker lockout with personal padlock and tag BREAKER OFF LOCKOUT DEVICE DANGER DO NOT OPERATE Name · Date · Machine ID Breaker handle held in OFF Lockout device blocks the handle Tag at thesame point
Figure 2: A breaker held off with a lockout device, a personal padlock and a tag (illustration only).

How to Safely Remove LOTO Devices and Restore Equipment

Follow OSHA 1910.147(e) before re-energising:

  1. Inspect the machine and work area. Remove tools and debris, and check that guards and components are back in place.
  2. Check that everyone is clear of the danger zone.
  3. Confirm the operating controls are in the off or neutral position.
  4. Remove each lock and tag. Each one must be removed by the person who applied it.
  5. Notify affected employees, then restore energy.

What if the person who fitted the lock is not available?

The employer may follow its written exception procedure. It must confirm the person is not on site, make reasonable efforts to contact them, and make sure they know the lock was removed before they return to work. A supervisor cutting off a lock for convenience is not this procedure.

If equipment must be re-energised briefly for testing, clear the area, remove the devices, energise and test, then de-energise and reapply the controls from step 1.

Group Lockout, Shift Changes and Contractors

What is group lockout/tagout?

Group lockout lets a crew work under one lockout while each person keeps personal protection. The keys for the isolating devices go into a group lock box. Every worker then adds a personal lock to the box and removes it when they finish.

  • A primary authorised employee is responsible for the group and checks each member’s exposure status.
  • When several crews are involved, one authorised employee coordinates control.
  • Nobody should work unless their own lock is on the box.
Group lockout with a lock boxIsolator AIsolator BIsolator CEach isolator is locked; its key goes into the boxGroup lock boxholds the keysPrimary authorisedWorker 2Worker 3Everyone adds a personal lock to the box
Figure 3: Group lockout with a lock box and personal locks (simplified).

LOTO during shift changes

The procedure must hand protection over in an orderly way, so there is never a gap. A common method is to overlap locks: the incoming worker fits their lock before the outgoing worker removes theirs.

LOTO procedures for contractors

The site employer and the contractor must exchange their lockout/tagout procedures before work starts. The site employer must also make sure its own staff follow the contractor’s restrictions.

Lockout/Tagout Exceptions: When Is LOTO Not Required?

Do not assume an exception applies

Exceptions have strict conditions. A job being short or routine is not enough.

ExceptionConditionsWatch out for
Minor servicing during productionThe work is routine, repetitive and integral to production, and alternative measures give effective protectionIt does not apply if a guard must be bypassed or a worker enters the danger zone
Cord-and-plug equipmentUnplugging removes the hazard, and the plug stays under the exclusive control of the person doing the workA plug left where others can reach it is not under your control
Hot tap on pressurised pipelinesContinuity of service is essential, shutdown is impractical, documented procedures are followed and special equipment gives effective protectionSpecialist work only

Does every maintenance task require LOTO?

No. Exposure to unexpected energisation or release decides it. If nobody can be exposed, LOTO is not triggered. If you are unsure, lock out.

Electrical Lockout/Tagout Procedure

Electrical work needs extra care. In the US, isolating a machine’s supply falls under 1910.147, but electrical work on utilisation installations is covered by OSHA Subpart S (1910.331 to 1910.335) and by the voluntary standard NFPA 70E. NFPA 70E is revised every three years, so check which edition applies to you.

An electrically safe work condition means the equipment has been disconnected from all sources, locked or tagged, tested to prove it is dead and, where needed, earthed (grounded). It removes the risk of electric shock and arc flash while you work.

Safety note

This guide explains principles only. Isolating and testing electrical equipment must be done by qualified people following the site’s electrical safety procedure.

Steps involved in electrical LOTO

  1. Identify every supply. Include second feeds, control power and back-feed. In a switchgear panel, check whether there is more than one incoming supply.
  2. Open the correct disconnecting device. Opening one feeder does not make the incoming supply or the busbars dead. To isolate a motor, open the disconnect upstream of the motor starter instead of relying on the starter.
  3. Lock and tag the disconnecting device.
  4. Release stored electrical energy, such as capacitors.
  5. Test for absence of voltage (see below).
  6. Earth (ground) where required. The terms differ between UK and US English; earthing vs grounding explains how.
  7. Keep locks and tags in place until the work is finished.

How to verify the absence of voltage

A qualified person must do this with a properly rated, inspected instrument, using the “live-dead-live” method:

  1. Prove the tester works on a known live source or proving unit.
  2. Test each conductor at the point of work.
  3. Prove the tester again on the known source.

UK guidance (HSE GS38) expects a two-pole voltage indicator that is proved on a proving unit before and after the test. Never rely on a switch position alone.

Lockout/Tagout Rules by Country

The law that applies depends on where the work happens. Do not assume OSHA’s rules apply in the UK or India.

CountryMain law and guidanceKey focusStatus
United StatesOSHA 29 CFR 1910.147 (general industry), 1910.269 (power utilities), 1926 (construction, for example 1926.417); ANSI/ASSP Z244.1; NFPA 70EWritten programme, procedures, training and annual inspectionOSHA rules are binding; ANSI and NFPA standards are voluntary unless adopted
United KingdomHealth and Safety at Work etc. Act 1974; PUWER 1998; Electricity at Work Regulations 1989; HSE HSG85, GS38 and HSG253Safe isolation and proving deadRegulations are binding; HSE guidance shows good practice
IndiaOSH Code, 2020 (in force 21 November 2025); Electricity Act, 2003 and CEA safety regulations; state rulesGeneral machinery and electrical safety dutiesDuties are binding; no detailed OSHA-style LOTO rule found in central text

United States

OSHA’s standard is the model for most LOTO guides. It requires written procedures, training, periodic inspection and the six-step sequence above. Some states run their own OSHA-approved plans, so check local rules.

United Kingdom

The UK has no single LOTO law. It uses the terms “safe isolation” and “lock-off”. Under the Electricity at Work Regulations 1989, regulation 12 requires means of cutting off the supply and isolation, regulation 13 requires precautions for work on equipment made dead, and regulation 14 allows live working only when strict conditions are met. PUWER regulation 19 requires suitable means to isolate work equipment from its energy sources. HSG85 gives practical electrical guidance. HSG253 covers isolation of process plant and is aimed mainly at oil, gas and chemical sites.

India

India’s four labour codes came into force on 21 November 2025. The Occupational Safety, Health and Working Conditions Code, 2020 replaced 13 earlier laws, including the Factories Act, 1948. Electrical safety is also covered by the Electricity Act, 2003 and the Central Electricity Authority safety regulations. Detailed LOTO steps usually come from company standards, so keep to a written procedure. Some state rules and licences continue during the transition, so confirm the current position with your state labour department or a qualified safety professional.

LOTO Training, Annual Inspections and Records

GroupWhat they must learn
Authorised employeesHow to recognise hazardous energy, its types and size, and how to isolate and control it, and how to apply, use and remove devices
Affected employeesThe purpose and use of the energy control procedure
Other employeesThe procedure, and the ban on restarting locked or tagged equipment
Employers must keep training records showing each employee’s name and training dates.

When is retraining required?

  • A change in job assignment.
  • A change in machines, equipment or processes that creates a new hazard.
  • A change in the energy control procedure.
  • An inspection that finds gaps, or a reason to believe someone’s knowledge is lacking.

How often should LOTO procedures be inspected?

At least once a year, by an authorised employee who is not using the procedure being inspected. The inspector reviews each authorised employee’s duties and any problems found must be corrected. The employer certifies the inspection, recording the machine, the date, the employees included and the inspector.

Lockout/Tagout Checklist: What to Check Before Starting Maintenance

Before work

  • ☐ Identify the machine and the task.
  • ☐ Review the machine’s written procedure.
  • ☐ List every hazardous energy source.
  • ☐ Notify affected employees.
  • ☐ Shut down the equipment.
  • ☐ Isolate all energy sources.
  • ☐ Apply your lock and tag to every isolating device.
  • ☐ Release or restrain stored energy.
  • ☐ Verify the zero-energy state.

After work

  • ☐ Inspect the machine and work area.
  • ☐ Check that everyone is clear.
  • ☐ Remove your own locks and tags.
  • ☐ Restore energy.
  • ☐ Notify affected employees.

This is a general checklist. It does not replace an approved, machine-specific procedure.

Lockout/Tagout Procedure Template: What It Should Look Like

Use this layout as a starting point for each machine. The example entries are illustrative only and must not be used on real equipment.

FieldInformation requiredIllustrative example
Machine nameEquipment identificationPacking line conveyor
Asset numberUnique machine IDC-12
DepartmentFacility locationPacking hall
Energy sourcesAll hazardous energy typesElectrical, mechanical, gravitational
Isolation pointsExact device locationsPanel B, breaker 14
Required devicesLocks, tags and other hardwareBreaker lockout, padlock, tag
ShutdownNormal shutdown instructionsStop line from the control station
IsolationSpecific isolation actionsOpen breaker 14
Stored energyRelease or restraint instructionsLower hopper, block it
VerificationZero-energy verification methodTry-out test, then voltage test by a qualified person
RestorationSafe re-energisation instructionsClear area, remove locks, notify staff
ApprovalSafety and qualified-person review, review datesName, date, next review

How to customise a LOTO procedure template

  1. Assess the specific machine for hazards.
  2. Identify every energy source.
  3. Record the real isolation points.
  4. Define how isolation will be verified.
  5. Have a qualified person review and approve it.
  6. Review it whenever the equipment or process changes.

Downloading or copying a template does not make you compliant. Only a procedure that matches your machine, and is reviewed on site, does.

Common Lockout/Tagout Mistakes to Avoid

  • Treating a stop button as isolation. Isolate at the energy-isolating device.
  • Missing a second supply or stored energy. Use an energy inventory and the drawings.
  • Skipping verification. Test every time.
  • Using someone else’s lock. One lock per person.
  • Cutting off a lock outside the procedure. Follow the employer’s removal procedure.
  • Using a tag where a lock is possible. Lock, unless equal protection is proved.
  • Using a generic procedure. Write one for each machine.
  • Dropping protection at shift change. Overlap the locks.

LOTO Violations, OSHA Penalties and Enforcement

Lockout/tagout is one of OSHA’s most cited standards. It ranked fourth in fiscal year 2025 (final data) with 2,562 citations. OSHA’s preliminary list for fiscal year 2026, covering 1 October 2025 to 31 August 2026, ranks it third.

OSHA top 10 most cited standards, FY2025 (final)Fall protection, general (1926.501)6,992Hazard communication (1910.1200)3,010Ladders (1926.1053)2,842Lockout/tagout (1910.147)2,562Respiratory protection (1910.134)2,294Scaffolding (1926.451)2,286Fall protection training (1926.503)2,216Powered industrial trucks (1910.178)2,150Eye and face protection (1926.102)1,965Machine guarding (1910.212)1,498
Figure 4: OSHA’s 10 most cited standards, fiscal year 2025, final citation counts. Source: OSHA data as reported by Safety+Health magazine.
Lockout/tagout share of FY2025 top 10 citations9.2%Lockout/tagout: 2,562Other nine standards: 25,253Total on the list: 27,815 citations
Figure 5: Lockout/tagout accounts for 9.2% of the 27,815 citations on the FY2025 top 10 list (our calculation from the counts above).

OSHA applied no inflation increase to penalties for 2026, so the 2025 maximums still apply:

Violation typeMaximum penalty (US dollars)
Serious or other-than-serious$16,550 per violation
Willful or repeat$165,514 per violation
Failure to abate$16,550 per day
Source: OSHA civil penalties memo, 21 May 2026. Proposed penalties are often lower than the maximum.

UK and Indian enforcement works differently, and penalty figures are not directly comparable.

On industrial machines, isolation also depends on how the equipment was built. Our NFPA 79 guide explains machine disconnects, wire colors and circuits that can stay live with the main switch off.

Light curtains are another safeguard that must never be bypassed during fault-finding. Our guide to light curtain safety relay troubleshooting shows how to trace OSSD, feedback and reset faults safely.

An emergency stop is not energy isolation; for how e-stops differ and what they must do, see our e-stop guide.

Frequently Asked Questions About Lockout/Tagout Procedures

What does LOTO stand for?

LOTO stands for lockout/tagout. It is a safety procedure that stops machines starting up, or releasing stored energy, while someone services them. Lockout uses a physical lock on the energy-isolating device. Tagout uses a warning tag. OSHA’s formal name for the rule is the control of hazardous energy.

What are the six steps of a LOTO procedure?

Prepare for shutdown, shut down the equipment, isolate every energy source, apply locks or tags, release or restrain stored energy, and verify that the equipment is isolated and de-energised. These follow OSHA 29 CFR 1910.147(d). Affected employees must be told before locks go on and after they come off.

What are the 8 steps of lockout/tagout?

Eight-step lists split the same job into smaller actions, usually adding employee notification at the start and restoration at the end. OSHA’s sample procedure in Appendix A also uses eight application steps. The regulation itself lists six elements, so follow the count used in your own written procedure.

What is a zero-energy state?

A zero-energy state means every source of hazardous energy has been isolated, released, blocked or restrained, so the equipment cannot move, start or release energy. You confirm it with a try-out test, gauge checks and, for electrical equipment, a voltage test by a qualified person.

Can someone remove another person’s LOTO lock?

Normally only the person who fitted a lock may remove it. If they are unavailable, the employer can follow a written exception procedure: confirm the person is not on site, make reasonable efforts to contact them, and make sure they know the lock was removed before they return to work.

How often must LOTO procedures be inspected?

At least once a year. The inspector must be an authorised employee who is not using the procedure being inspected. They review each authorised employee’s duties, correct any problems and certify the inspection, recording the machine, the date, the employees included and the inspector’s name.

Is lockout required before every maintenance task?

No. LOTO applies when someone could be hurt by unexpected start-up or release of energy during servicing. Narrow exceptions exist, such as cord-and-plug equipment under the worker’s exclusive control, or routine minor servicing with effective alternative protection. Check the exact conditions before relying on any exception.

What is the difference between a LOTO programme and a LOTO procedure?

The programme is the employer’s overall system: written procedures, training and annual inspections. A procedure is the machine-specific instruction sheet that shows how to isolate and verify one machine, or a group of similar machines. An employer needs both.

Is lockout/tagout required in India?

India’s publicly available central rules do not set out an OSHA-style written LOTO standard in detail, but employers must still protect workers from machinery and electrical hazards. The OSH Code, 2020 came into force on 21 November 2025 and replaced the Factories Act, 1948. Check current central and state rules.

What is electrical lockout/tagout?

It is the process of making electrical equipment safe to work on: identify every supply, open and lock the disconnecting device, release stored energy, test for absence of voltage with a proved instrument, and earth where required. In the UK this is called safe isolation. Only qualified people should do it.

Final Thoughts on Lockout/Tagout Procedures

A lockout tagout procedure works because it removes energy at the source and proves it has gone. Follow the six steps in order, write a procedure for each machine, train everyone involved and check the system every year. LOTO is a safety practice, not a machine shutdown checklist.

Sources and Further Reading

Disclaimer

This article is general information, not legal, compliance or engineering advice. Templates and checklists are starting points and must be adapted to your equipment, reviewed by a qualified person and checked against the law where you work. Penalty figures, rankings and standard editions change; check the official sources above. Last verified: 8 November 2026.

About the author