Under the NEC, cable trays follow Article 392 and underground cable trenches follow Section 300.5. Trays must form a continuous, bonded, accessible system and respect fill limits. Buried cables and raceways must meet the minimum cover in Table 300.5, commonly 24 inches for direct-burial cable in general locations. Any trench must also meet OSHA excavation safety rules.
| Topic | Cable tray | Underground trench |
|---|---|---|
| Main NEC reference | Article 392 | Section 300.5 |
| Access | Must remain accessible | Buried, so harder to change |
| Main limit | Fill, support and bonding | Minimum cover and backfill |
| Protection | Location and covers | Depth, raceway and warning ribbon |
| Best for | Plants with changing circuits | Routes between buildings or equipment |
Cable Tray Requirements
The NEC treats a cable tray as a structural system for securely fastening or supporting cables and raceways. ABB’s Cable Tray Technical Guide (2020) summarizes these key rules:
| Rule | Requirement | NEC section |
|---|---|---|
| Continuous system | Mechanical breaks are allowed, but a bonding jumper must keep electrical continuity | 392.18(A) |
| Complete first | Each run must be complete before cables are installed | 392.18(B) |
| Walls and floors | Penetrations must limit the spread of smoke and fire | 392.18(D), 300.21 |
| Accessible | Must not be permanently enclosed in the building structure | 392.18(E) |
| Working space | Leave enough room for installation and maintenance | 392.18(F) |
| Over 600 V marking | Permanent high-voltage warning at intervals of no more than 10 ft | 392.18(H) |
| Mixed voltages | Over 600 V needs a separator from lower voltage unless Type MC | 392.20(B) |
| Single conductors | 1/0 AWG or larger, marked for tray use, in qualifying industrial sites | 392.10(B)(1) |
Grounding and bonding
A metal tray must be electrically continuous and grounded. The Cable Tray Institute explains that NEC 392.60 allows it to serve as the equipment grounding conductor where qualified people maintain the system and all conditions in that section are met. Otherwise, run a separate equipment grounding conductor. See our ground wire size chart for sizing background.
Fill: worked examples for ladder or ventilated tray
ABB’s guide gives these minimum width formulas, where W is inside tray width in inches:
| Cable type | Rule | Example | Result |
|---|---|---|---|
| Multiconductor smaller than 4/0 | W ≥ 0.855 × total area | Total area 10 in² | W ≥ 8.55 in, use 9 in |
| Multiconductor 4/0 or larger | W ≥ sum of diameters, single layer | Five 2 in cables | W ≥ 10 in, use 12 in |
| Control or signal | W ≥ 2 × total area ÷ usable height | 6 in², 4 in usable height | W ≥ 3 in, use 6 in |
Solid-bottom tray and mixed cable loads use different limits, so read Section 392.22 directly. Fill is only one check. You also need ampacity, because cable grouping and airflow affect it. Our AWG ampacity chart and guide to electrical cables can help.
Underground Trench Requirements
Minimum cover depths
| Location | Direct-burial cable | RMC or IMC | Nonmetallic raceway listed for burial |
|---|---|---|---|
| General locations | 24 in | 6 in | 18 in |
| In trench below 2 in of concrete | 18 in | 6 in | 12 in |
| Under streets, roads, alleys, driveways and parking lots | 24 in | 24 in | 24 in |
| Solid rock, under at least 2 in of concrete | Raceway only, 2 in | 2 in | 2 in |
Other Section 300.5 rules
| Item | Requirement |
|---|---|
| Emerging from grade | Protect up to at least 8 ft above grade. Below grade, protection need not extend more than 18 in |
| Service conductor ribbon | At least 12 in above the conductors |
| Backfill | No large rocks, concrete chunks, steel rods, mesh or sharp objects |
| Moisture | Seal raceways at one or both ends where moisture could reach live parts |
| Raceway ends | Use a bushing or fitting where a raceway ends underground |
| Ground movement | Allow for settlement or frost, such as with S loops or expansion fittings |
| Same circuit | Keep conductors together in a raceway, cable or close together in the trench |
| Inside underground raceways | Treated as a wet location |
Worked example: trench depth
A 1 in direct-burial cable runs through a general outdoor location that needs 24 in of cover. Because cover is measured to the top of the cable, the bottom of the cable sits at least 25 in below finished grade. Dig deeper if you need bedding, and measure from final grade, because later landscaping can reduce the cover.
Trench Safety
Cave-ins are the greatest risk to people working in trenches. OSHA’s fact sheet sets out these requirements:
| Trench condition | OSHA requirement |
|---|---|
| 5 ft or deeper | Protective system required unless entirely in stable rock |
| Less than 5 ft | A competent person may determine that no protective system is needed |
| 20 ft or deeper | System designed by a registered professional engineer, or based on approved tabulated data |
| Before entry | Competent person inspects daily and as conditions change |
| Spoil | Keep soil and materials at least 2 ft from the edge |
| More than 4 ft deep | Test for low oxygen, hazardous fumes and toxic gases |
Installation Checklist
- Confirm the code edition and any local amendments.
- Select the route and check the environment, including hazardous locations.
- Size conductors and protection, including the breaker rating.
- Check tray fill or burial cover for the chosen wiring method.
- Complete and bond the tray before pulling cable.
- Inspect the trench and backfill before closing it.
- Test insulation with a megger before energizing.
- Record the as-built route, especially for buried cable.
For the equipment at each end of the route, see our guide to what switchgear does.
Frequently Asked Questions
What is the difference between cable trays and trenches?
A cable tray is an exposed structural support system, usually indoors or on racks. A trench carries buried cables or raceways underground.
Which NEC article covers cable trays?
Article 392 covers cable trays. Article 300, including Section 300.5, covers underground installations.
How deep should a direct-buried cable be?
A common general value in Table 300.5 is 24 inches of cover, but it depends on wiring method and location. Check the table in your adopted code.
How is burial depth measured?
Cover is the shortest distance from the top of the cable or raceway to finished grade, concrete or similar cover.
Can power and control cables share a cable tray?
Multiconductor cables rated 600 V or less can share a tray. Cables over 600 V need a separator unless they are Type MC, according to ABB’s summary of NEC 392.20.
Can a metal cable tray be the equipment grounding conductor?
It can in qualifying installations under NEC 392.60, where qualified people maintain the system and the tray meets the section’s conditions.
Do underground cables need warning tape?
Underground service conductors need a warning ribbon at least 12 inches above them under 300.5(D)(3). It is often good practice on other circuits too.
When does a trench need a protective system?
OSHA requires one at 5 feet or deeper unless the excavation is entirely in stable rock. Below 5 feet, a competent person may decide it is not required.
Sources and Further Reading
- ABB: Cable Tray Technical Guide (2020): tray types, Article 392 rules and fill.
- Cable Tray Institute: Technical Bulletin 11: equipment grounding conductors for cable tray.
- EC&M: Requirements for Underground Cables and Raceways (2017 NEC): Section 300.5.
- EC&M: NEC Requirements for Installing Raceways and Cables Underground (2020 NEC): Section 300.5.
- UpCodes: Minimum Cover Requirements, Table E3803.1 (Table 300.5): cover depths from a 2024 residential code.
- OSHA: Trenching and Excavation Safety Fact Sheet: trench protection.
